Do A Quick Check first. Then choose one of B, C or D. Write your answers in your book or note guide.
A Quick Check
Identify | tap an answer for instant feedback
1. A Gantt chart shows:
2. The critical path is:
3. If a task on the critical path is delayed:
4. Sequencing is:
B Short Answer
Explain, Identify
1. Explain how Gantt charts and critical path analysis help operations managers. (4 marks)
Write your answer in your book first. Then open the marking guide and mark it yourself.
Show the marking guide
| Marks | What it looks like |
|---|---|
| 4 | Clear cause and effect, with a relevant example |
| 3 | Sound answer, less detail or no example |
| 2 | Describes with little explanation |
| 1 | Some relevant information |
Answers could include:
- Gantt charts show tasks, timing and overlap so progress can be tracked
- Critical path analysis identifies tasks that cannot be delayed
- Helps allocate resources, set deadlines and avoid delays
- Example
2. Tasks: A (3 days, starts first), B (2 days, after A), C (4 days, after A), D (1 day, after B and C). Identify the critical path and the minimum project time. (2 marks)
Write your answer in your book first. Then open the marking guide and mark it yourself.
Show the marking guide
| Marks | What it looks like |
|---|---|
| 2 | Correct, clear answer that addresses the question |
| 1 | Some relevant information |
Answers could include:
- Critical path: A, C, D
- Minimum project time: 8 days (3 + 4 + 1). B has 2 days of slack.
C Mini Business Report
Recommend | Outcomes H8, H9
Task: Recommend how Rapid Renos can use sequencing and scheduling to complete jobs on time.
About 250 words, written as a business report. Headings: Introduction / Current situation / Recommendations / Conclusion.
Check your report: a high-level response would include
- Identifies poor sequencing and scheduling as the cause
- Recommends a Gantt chart for every job, shared with all trades
- Recommends critical path analysis to identify tasks that cannot slip
- Recommends ordering materials ahead and monitoring progress weekly
D Case Study Collector
Analyse | Outcome H7
Business: Snowy 2.0 (Snowy Hydro)
Research and add to your Operations Case Study Bank:
- What the project is
- How far it has run over time and budget, with source and date
- One cause of the delays
- How better scheduling might have helped
Use a reliable source from the last 3 years where you can. Record the source name and date.
Check your entry: what to look for
- Accurate, dated figures from reliable sources
- Links delays to sequencing, scheduling or the critical path
- A reasoned judgement