OPS-P4  |  OPERATIONS PROCESSES

Transformation processes - sequencing and scheduling - Gantt charts, critical path analysis

Outcomes: H4, H5

Do A Quick Check first. Then choose one of B, C or D. Write your answers in your book or note guide.

A  Quick Check

Identify  |  tap an answer for instant feedback

1. A Gantt chart shows:

2. The critical path is:

3. If a task on the critical path is delayed:

4. Sequencing is:

B  Short Answer

Explain, Identify

1. Explain how Gantt charts and critical path analysis help operations managers. (4 marks)

Write your answer in your book first. Then open the marking guide and mark it yourself.

Show the marking guide
MarksWhat it looks like
4Clear cause and effect, with a relevant example
3Sound answer, less detail or no example
2Describes with little explanation
1Some relevant information

Answers could include:

  • Gantt charts show tasks, timing and overlap so progress can be tracked
  • Critical path analysis identifies tasks that cannot be delayed
  • Helps allocate resources, set deadlines and avoid delays
  • Example

2. Tasks: A (3 days, starts first), B (2 days, after A), C (4 days, after A), D (1 day, after B and C). Identify the critical path and the minimum project time. (2 marks)

Write your answer in your book first. Then open the marking guide and mark it yourself.

Show the marking guide
MarksWhat it looks like
2Correct, clear answer that addresses the question
1Some relevant information

Answers could include:

  • Critical path: A, C, D
  • Minimum project time: 8 days (3 + 4 + 1). B has 2 days of slack.

C  Mini Business Report

Recommend  |  Outcomes H8, H9

Rapid Renos completes kitchen renovations in Newcastle. Jobs often run two to three weeks late because tradespeople arrive in the wrong order and materials are not ready when needed. Customers are leaving bad reviews.

Task: Recommend how Rapid Renos can use sequencing and scheduling to complete jobs on time.

About 250 words, written as a business report. Headings: Introduction / Current situation / Recommendations / Conclusion.

Check your report: a high-level response would include
  • Identifies poor sequencing and scheduling as the cause
  • Recommends a Gantt chart for every job, shared with all trades
  • Recommends critical path analysis to identify tasks that cannot slip
  • Recommends ordering materials ahead and monitoring progress weekly

D  Case Study Collector

Analyse  |  Outcome H7

Business: Snowy 2.0 (Snowy Hydro)

Research and add to your Operations Case Study Bank:

  • What the project is
  • How far it has run over time and budget, with source and date
  • One cause of the delays
  • How better scheduling might have helped

Use a reliable source from the last 3 years where you can. Record the source name and date.

Check your entry: what to look for
  • Accurate, dated figures from reliable sources
  • Links delays to sequencing, scheduling or the critical path
  • A reasoned judgement